Grange Close Development - Louth, Ireland
Specifications
Category—Louth Co. Council engaged with HTL on the pilot project utilising 3DCP technology at the site in Dundalk. Executed by B&C Building Contractors Ltd, the 330sqm superstructure was completed in 12 days, after which traditional building works commenced. Our collaboration with Roadstone Ltd has resulted in Flomix, the lowest embodied carbon 3D printable RMC globally at 295kg CO2/m³ used to 3D print the Grange Close scheme.
Machinery - BOD2
Location - Louth, Ireland
3D-printing rendered by - HTL.tech and Harcourt Architects
Preparation - 3 Days Set-up & Set-down
Printing - 12 days to print superstructure
Site operation time - 18 days total on site
Overall project completion time - 132 working days (35% faster than traditional methods)
Project Overview
Volume
330 m2 (~3,550 sq ft) in 2 floors over 3 units
Print time
Superstructure Print time: 12 days (June 19th - July 9th)
Ground floor: 7 days
Top floor: 5 days
Stats
Load-bearing structural concrete
BCAR-compliant design
NZEB accreditation
Build